|
|
|
TARGET'S
MACHINE BASE GROUT - DELTA PORT - BRITISH COLUMBIA
|
|
DELTA, British Columbia
February 2009 and Levelton Consultants
were looking at a grout specification for grouting under the crane rails
for the new third berth at DeltaPort.
They needed a high strength
grout that would be subject to heavy cyclical loads as the new cranes
would be able to lift larger loads than their other cranes. Though
scrutinizing many products, many would not meet the tight specification.
In discussion with Jack Torok of
Target Products/Quikrete, TARGET Machine Base Grout was selected but
not before under going analysis by various test
methods. Throughout April and into May, the tests were analyzed and
TARGET Machine Base Grout not only met the requirements but well exceeded them.
Grouting commenced in earnest in
late April and was completed by June 2009. From all final testing that
was conducted on site, the product performed admirably.
Deltaport's Third Berth opened to
much fanfare and business on January 18, 2010
|
|
Existing Delta Port Terminal - 2009
Setting the plate for the Rail
|
 |
|
Generator driving the Mixer.
TARGET Machine Base Grout bags in foreground
 |
|
Pumping TARGET Machine Base Grout under crane rail

For further information on
this product, TARGET Machine Base Grout, contact Jack Torok @ 1.800.575.7700
|
|
TARGET'S
1121 CABLE DUCT GROUT - THE WILLIAM R BENNETT BRIDGE - KELOWNA
KELOWNA, British Columbia
The William
R Bennett Bridge was constructed to be a center piece of the
Okanagan’s busy transportation infrastructure. Its workload would
consist of greater than 50,000 vehicles daily. With the selection of SNC
Lavalin to design, build, finance and operate the new bridge, immense
pressure was placed upon the group of the many contractors to complete
the bridge on time, on budget and with emphasis on quality construction
to allow the new bridge to perform a long time in service.
With this
in mind, one of the key components of the design was to have a high
quality Post Tension Cable Duct Grout utilized for grouting in the duct
work as well as tendons in each of the pre cast concrete sections. To
qualify the various manufacturers’ grouts that existed in the market
place, testing had to be conducted.
After reducing the list to
three quality manufacturers, the grout was tested in real world trials.
Harris Rebar, in co-operation with Target’s
Jack Torok and Richard Atkinson, commenced testing at Vancouver
Wharves in
North Vancouver
. Harris Rebar was responsible for grouting and was therefore
responsible for full testing of the final selected grout. Target’s
1121 Cable Duct Grout not only showed superior flowability
characteristics, but was the only grout that could completely fill the
ducts without leaving any void space as well as fully encapsulating the
steel strands it also or showed no sign of bleed water, even under high
pressure grouting.
|
|
Kelowna
Floating Bridge Construction - Sept
2007 Viewing Outflow Valves on Pontoon 7  
|
|
William R.
Bennett Bridge in use September 2008 
In the myriad of different
products used for the construction of this bridge, the Target Brands
included: Target Portland
Expanding Grout, Target
Aquaplug, Target Sacking
Mix, Target Silica Sand,
and Target 1121 Cable Duct Grout.
For further information on any of
these products, contact Jack Torok @ 1.800.575.7700
|
|
ACQUISITION OF TARGET PRODUCTS ENABLES
THE QUIKRETE® COMPANIES TO EXPAND INTO WESTERN CANADA
|
|
ABBOTSFORD, British Columbia (Feb. 8, 2008) – Target Products, Ltd., the leading producer of dry mix concrete and cement related products in Western Canada, announced today that it has been acquired by The QUIKRETE® Companies, North America’s largest manufacturers of packaged concrete.
“The QUIKRETE® Companies are known for offering superior quality, product depth and distribution capability,” said Neil Duke, former principal of Target Products. “We are excited about the opportunity to contribute to the continued growth and availability of this highly respected brand in the Canadian commercial building and home improvement industries.”
[Read More...]
Bulletin to our Valued Customers & Suppliers
|
|
INDUSTRIAL
MORTAR DIVISION
|
Target
acquired a Spec Mix® license in 2007 and sales have grown
unbelievably fast. The Masons have realized the cost and time savings to
their companies and have taken to the Spec Mix
Silo system. This picture
shows our silos in place on a jobsite (the project is
Lawrence Grassi Middle School expansion) in Canmore, Alberta..
For
more information, contact:
Target
British Columbia -
Jack Torok @ 1.800.575.7700
Target
Alberta
- Tom Bartley @ 1.800.661.8482
|
|
NEW USE FOR PROVEN PRODUCT
-
PORTLAND EXPANDING GROUT
|
|
International
Construction Services, contracted by the Sonora Lodge in Campbell River
BC were working on a deck for their resort. After speaking with Target's Jack
Torok, the product Portland Expanding Grout was recommended for the tops
of the columns (as a leveling base) and also between the pre-cast
panels to fill the space between the panels. Installation was successful and progressed slightly ahead of
schedule. Portland Expanding Grout is working very well for
International Construction Services. Here are some photographs of the
completed project.

|
|
NEW PRODUCT - VERTICAL
OVERHEAD (V/O) REPAIR MORTAR
|
|
A
long awaited product, Target’s new Vertical/Overhead
Repair Mortar has been in formulation and testing for over three
years. Helen Zeng (R& D Senior Materials Engineer) had managed to
formulate a product that was sticky enough to be applied overhead yet
still be workable that it could be troweled and finished to a smooth
appearance. The question…were there enough sales to justify it’s
existence?
The
answer came by way of a phone call from Phil Beedle, Senior Construction
Engineer from BC Hydro to Jack Torok (Target's Industrial Sales Technical
Representative). BC Hydro’s power station, The Cheakamus Power
Generating Station, 10 kilometers west of Squamish, was constructed in
1959 to supply the timber mills of Squamish and send excess power to
Vancouver. By 2005 it had grown to supply power to the entire
communities of Squamish, Whistler and still send excess power to
Vancouver. Unfortunately the exterior of the plant was left largely
neglected and was in bad need of refinishing. BC Hydro originally
bantered around Shotcreting the wall, but this would be next to
impossible considering they are situated on a salmon spawning river. The
V/O Repair Mortar made perfect sense. The first trial of the V/O Repair
Mortar was done
in October of 2004 on an exposed concrete wall at the plant to determine
if the product could withstand a cold winter along with the varying
temperatures that occur in that valley. After a site visit in January
and again in May, the product came through with flying colours. BC Hydro
was sold on using the V/O Repair Mortar. They ordered up 5 pallets of
the material and began and completed the entire job in little over a
week. The application crew stated that they have never used a product
that mixed up as easy and was as quick to use with excellent results as
Target’s V/O Repair Mortar.
|
|
TARGET SOLVES UNDERWATER GROUTING
PROBLEMS IN SAN FRANCISCO BAY
|
| San
Francisco
is a beautiful city famous for both the bay it is named after and the
bridges that cross it. As is the case with all bridges, particularly
those over salt water and in very active seismic areas, these structures
needed upgrading. The longest of these bridges is the one between
Richmond and San Rafael.
The upgrading of this structure is a $450,000,000 U.S. project that
requires an extraordinary amount of work on the piers below the low tide
line. This is an environmentally sensitive area and the work had to be
carried out while the bridge was still in service. To address these and
other problems the owner developed a specification for the grout
required in the annular space between the existing pier and the new
seismic collars. Target
Products
got the call to design a grout to meet that design specification and the
placability requirements of the contractor. The result was Target
Anti-washout Grout.
Target
started supplying material in September of 2001 and will continue until
this phase of the project is complete, probably in 2004.
|
|