Dry-Shotcrete Production at Antamina (Peru)
|
Project:
|
Antamina is the largest mining project underway in Peru
(over USD $2 billion). Shotcrete project involves a decant tunnel and
shaft to take excess water from the tailings dam in case of unexpected
rainfall.
|
|
Year:
|
1999/2000
|
|
Owner:
|
Compañía
Minera Antamina (Noranda – Rio Algom – Teck)
Construction management by Bechtel, USA
Tunnel Design: Golder, Canada
|
|
Contractor:
|
Redpath
Mas Errazuriz Peru
RME Project Manager: Denis Blais
Bechtel Project Manager: George Manson
|
|
Client:
|
Redpath
Mas Errazuriz Peru
|
|
Volume:
|
Approximately 2,000 cubic meters in 120 days.
|
|
Operation:
|
High quality dry shotcrete was produced within 7 days
of signing of contract, allowing the contractor to have packaged
shotcrete at the startup of the project available 24 hours per day at
both faces, with zero waiting time for shotcrete production at the site.
Within 30 days the tunnel was progressing at 4 rounds a
day and 40 cubic meters of shotcrete were being successfully applied in
24 hours.
- Target Standards of quality and mix
design.
- Target Set Accelerator, Silica Fume
and Steel Fibers were imported into Peru via sea freight and added
to Portland Cement and sand conforming to ACI No 2 shotcrete
gradation specified by Bechtel.
|
|